Publisher's Synopsis
As described in this report, the authors explored that operating under continuing resolutions (CRs) at the beginning of a fiscal year (FY), which has become the norm for the past several years, has led to delays and increased costs in U.S. Department of Defense (DoD) weapon procurement. Purportedly, operating under a CR causes these effects by constraining initiation of activities not previously approved and funded. The authors used data drawn from successive President's budget submissions to compare projected and realized award dates and unit costs for 151 procurement awards that DoD made for FYs 2013 through 2015, which had the two longest CRs in recent history. They also compared outcomes of procurement awards originally projected for FY 1999, which had only three weeks under CRs, with those for FYs 2013 through 2015. A qualitative analysis comparing anticipated and actual results of procurement awards about which DoD staff had expre